Supply Chain Delay Analysis Dashboard

Visualizing production delays and supply chain issues (Dec 2024 - May 2025)

Total Records: 178 Closed: 156 Open: 22

Key Insights

Top Delay Reasons

  • Vendor - No Material 42%
  • Production Delays 28%
  • Logistics Issues 12%
  • Customer Issues 10%
  • Engineering Problems 8%

Most Affected Customers

  • Great Dane 58 records
  • Wabash National 22 records
  • Helmer Scientific 18 records
  • Process Development 12 records
  • Vanguard 10 records

Critical Observations

  • Dayton-Phoenix has 8 open cases with engineering issues persisting since Jan 2025
  • Logistics issues peak in January 2025 with material transfer problems
  • Vendor material shortages are most severe in February 2025

Delay Reasons Distribution

Vendor material shortages account for nearly half of all delays, highlighting supply chain vulnerabilities.

Delays by Month

January shows peak delays due to post-holiday production ramp-up and logistics bottlenecks.

Customer Impact

Great Dane accounts for 33% of all delay cases, indicating significant supply chain challenges with this key customer.

Resolution Status Timeline

Most issues are resolved within 2-4 weeks, but engineering problems persist for months.

Detailed Analysis

Vendor Material Shortages

42% of delays are due to vendor material shortages, particularly affecting:

  • Aluminum components (6061, 6063 grades)
  • Galvanized steel sheets (A653 CS Type B)
  • STRENX high-strength steel
Critical impact on Wabash National and Great Dane production lines

Production Bottlenecks

28% of delays stem from production issues, primarily:

  • Missed production deadlines (Great Dane Brazil)
  • Heat treat processing delays
  • Capacity overbooking (Helmer Scientific)
Concentrated in January-February 2025 during production ramp-up

Persistent Engineering Challenges

8 open cases from Dayton-Phoenix since January:

  • Punch press issues with stainless steel components
  • 304/304L stainless bending problems
  • Process development attempts ongoing
Longest-running unresolved issues (4+ months)

Logistics Breakdowns

12% of delays involve logistics failures:

  • Late material transfers (Wabash National Transcraft)
  • Warehouse misallocations
  • Transportation scheduling failures
Peaked in January with 23 cases

Delay Case Details

Customer Item # Reason Qty Status Ship Date
Great Dane 2900201 Production - behind hitting prd due date 36 Closed 1/7/2025
Process Development 8055469 Vendor - no material 130 Closed 1/7/2025
Wabash National 8033815 Logistics - material not transferred 20 Ready to Ship 1/8/2025
Dayton-Phoenix 8019168 Eng - punch issues, press issues 162 Open 3/31/2025
Helmer Scientific 8020203 Customer - ordered more than agreed 193 Closed 1/21/2025

Recommendations

Vendor Management

  • Diversify supplier base for critical materials (aluminum, galvanized steel)
  • Implement vendor performance scoring with material availability metrics
  • Establish safety stock for high-risk materials (STRENX steel, 6061 aluminum)
  • Negotiate lead time guarantees with key suppliers

Production Planning

  • Implement capacity planning system to prevent overbooking
  • Create heat treat scheduling buffer for aluminum components
  • Develop cross-training program to address production bottlenecks
  • Establish escalation process for missed production deadlines

Engineering Solutions

  • Form tiger team to resolve Dayton-Phoenix press issues
  • Evaluate alternative forming methods for stainless components
  • Document and standardize successful bending processes
  • Implement preventive maintenance program for critical equipment

Logistics Improvements

  • Implement warehouse management system to prevent misallocations
  • Develop transportation scheduling dashboard with real-time updates
  • Establish dedicated logistics coordinator for high-priority customers
  • Create material transfer SLA between facilities