Visualizing production delays and supply chain issues (Dec 2024 - May 2025)
Vendor material shortages account for nearly half of all delays, highlighting supply chain vulnerabilities.
January shows peak delays due to post-holiday production ramp-up and logistics bottlenecks.
Great Dane accounts for 33% of all delay cases, indicating significant supply chain challenges with this key customer.
Most issues are resolved within 2-4 weeks, but engineering problems persist for months.
42% of delays are due to vendor material shortages, particularly affecting:
28% of delays stem from production issues, primarily:
8 open cases from Dayton-Phoenix since January:
12% of delays involve logistics failures:
| Customer | Item # | Reason | Qty | Status | Ship Date |
|---|---|---|---|---|---|
| Great Dane | 2900201 | Production - behind hitting prd due date | 36 | Closed | 1/7/2025 |
| Process Development | 8055469 | Vendor - no material | 130 | Closed | 1/7/2025 |
| Wabash National | 8033815 | Logistics - material not transferred | 20 | Ready to Ship | 1/8/2025 |
| Dayton-Phoenix | 8019168 | Eng - punch issues, press issues | 162 | Open | 3/31/2025 |
| Helmer Scientific | 8020203 | Customer - ordered more than agreed | 193 | Closed | 1/21/2025 |